Highway 413 / Bradford Bypass
>$10BCost to Ontario
19 sources ↓TL;DR
Ford revived two cancelled highway megaprojects — the $8.6–12 billion Highway 413 and the $2–4 billion Bradford Bypass — despite independent studies showing negligible traffic benefits. Developers who own thousands of acres along both routes donated over $800,000 to Ford's PCs. Both projects were shielded from meaningful federal environmental review.
What was promised
Ford on Highway 413's price: 'I'll get the exact number for you'
“We've been pretty transparent on costs. I'll get the exact number for you.”
Doug Ford, · Highway 401 tunnel news conference, Toronto
What happened · Aug 27, 2025
Ford's staff refused to give the figure right after the news conference, and as of June 2026 the government had still never said what Highway 413 is expected to cost, even after awarding its first contracts.
On September 25, 2024, The Trillium asked Ford whether he would release Highway 413's projected cost, and he promised an exact figure. After the news conference his staff declined, saying the estimate had to stay confidential until procurement was finished and contracts were awarded. The first two Highway 413 contracts were announced on August 27, 2025, but Ford and Transportation Minister Prabmeet Sarkaria again would not give a budget or completion date. On June 5, 2026, The Trillium reported that the government 'has never said how much the project is estimated to cost', after the opposition parties asked the Financial Accountability Office to cost the highway.
Promise: The Trillium, The Trillium
Outcome: Toronto Star, The Trillium, Toronto Star
Ontario said Highway 413 was 'subject to' the Environmental Assessment Act, then exempted it
“Highway 413 is subject to Ontario's Environmental Assessment Act and other provincial and federal protections, including those under the Fisheries Act, the Migratory Birds Convention Act and the Species at Risk Act.”
Ontario government news release, · Ontario news release, Caledon
What happened · Nov 25, 2024
Within seven months the government passed Bill 212, whose Schedule 3 (Highway 413 Act, 2024) exempts Highway 413 and its early works from the Environmental Assessment Act.
On April 15, 2024, a joint Canada-Ontario release announcing that the federal impact-assessment designation would be set aside said the project 'is subject to Ontario's Environmental Assessment Act', and the province repeated this on April 30, 2024. On October 21, 2024, Transportation Minister Prabmeet Sarkaria introduced Bill 212, the Reducing Gridlock, Saving You Time Act, 2024. Its Schedule 3, the Highway 413 Act, 2024, exempts the highway, its extensions and its early works from the Environmental Assessment Act. It also disapplies Part II of the Environmental Bill of Rights to permits for the project and replaces the EA with a ministry-run environmental impact assessment report. The bill received royal assent on November 25, 2024; the draft report was open for comment from December 1, 2025 to January 6, 2026, and the final report was published on March 12, 2026.
Ford: Highway 413 construction 'will begin in 2025'
“I'm thrilled to announce that construction on this highway will begin in 2025. We're already starting field work and land acquisition that will help make sure we get shovels in the ground on time.”
Doug Ford, · News conference, Caledon
What happened · Aug 27, 2025
Work began in August 2025, but on existing roads (Highway 10 resurfacing and the 401/407 interchange); the bid to build the first stretch of the new highway opened only on September 1, 2026.
On August 27, 2025, Ford announced in Caledon that the first two Highway 413 construction contracts had been awarded: resurfacing Highway 10 to prepare for a bridge over the future highway, and an embankment at the Highway 401/407 interchange that will be the highway's western terminus. A December 9, 2025 release said the 401/407 interchange upgrades were complete. These were early works on existing highways; the notice of procurement to design and build the first mainline section (the east third, Highway 400 to west of The Gore Road) was issued on September 1, 2026. Ford and Transportation Minister Prabmeet Sarkaria declined in August 2025 to give a completion date or total cost.
Who benefited
- Fermar Paving
CBC reported Fermar Paving was awarded the first Highway 413 construction contract, for an embankment at the Highway 401/407 interchange.
Source: Construction starting on Highway 413, Ontario premier says — CBC Toronto (Aug 27, 2025), Ontario begins Highway 413 construction despite Greenbelt, endangered species concerns — GTA Construction Report (Aug 29, 2025)
- Pave-Al
CBC reported Pave-Al was awarded the second Highway 413 contract, for resurfacing Highway 10 in Caledon to prepare for a bridge over the future highway.
Source: Construction starting on Highway 413, Ontario premier says — CBC Toronto (Aug 27, 2025), Ontario begins Highway 413 construction despite Greenbelt, endangered species concerns — GTA Construction Report (Aug 29, 2025)
Promise: Caledon Citizen, Ontario Newsroom
Outcome: Ontario Newsroom, Ontario Newsroom, Ontario Newsroom, CBC News
Who benefited
- Silvio De Gasperis
TACC Corporation and affiliated companies began acquiring land near the Bradford Bypass route immediately after the 1997 environmental assessment. With the Ford government reviving the project, those holdings stand to increase substantially in value. The DeGasperis consortium employed both Peter Van Loan and Frank Klees as lobbyists targeting Transportation Minister Mulroney and Premier Ford.
- TACC (TACC Construction / TACC Developments, De Gasperis family)
A National Observer/Torstar investigation found companies connected to the De Gasperis/TACC family own three properties totalling 168 acres near the proposed Highway 413 route, plus five more properties jointly owned with other developers — land whose value would rise if the highway is built.
- January Properties · $20.5M for 94 acres
January Properties, with three (unnamed in source) DeGasperis family members listed as directors according to corporate records, paid $20.5 million for a 94-acre parcel of land in Holland Landing near the proposed Bradford Bypass route in September 2017 — four months after the highway project was revived by the Ford government.
- 413 Continuity Partners (AECOM–WSP joint venture)
Won the Highway 413 program-management contract in July 2026, according to the province's September 1, 2026 release. No contract value was given, and no source alleges anything improper about the award.
Source: Ontario Taking Next Steps to Build Highway 413 — Ontario Newsroom
- Parsons–Egis Joint Venture (Parsons Inc. / Egis Canada Ltd.)
Won the detail design contract for the Highway 413 central contract, including the 410 Extension, in June 2026, according to the province's September 1, 2026 Highway 413 release. No contract value was given.
Source: Ontario Taking Next Steps to Build Highway 413 — Ontario Newsroom
Key: People Related scandals
Why it matters
The Highway 413 corridor runs through 2,000 acres of farmland, crosses 85 waterways, paves over nearly 400 acres of protected Greenbelt land, disrupts 220 wetlands, and threatens the habitat of 10 species at risk. The Bradford Bypass would cut through 27 waterways and 11 hectares of sensitive wetlands in the Holland Marsh — a region sometimes called "Ontario's vegetable garden" for its highly fertile soils and agricultural significance.
The developer connection is extensively documented. A 2021 investigation by National Observer and Torstar found that 3,300 acres of land along the Highway 413 route were owned by just eight major property developers, most of them prolific PC donors. Developers with land along the corridor donated at least $753,000 to Ford's Progressive Conservatives. The DeGasperis family and their company TACC Construction alone donated over $55,000, while employing former Conservative MP Peter Van Loan as a lobbyist registered specifically to influence "the impact of the proposed highway on client's lands."
Along the Bradford Bypass corridor, the pattern repeated: property records showed members of the DeGasperis family began buying up lands near Bradford shortly after Ford revived the project in 2019. January Properties — with three DeGasperis family members listed as directors — paid $20.5 million for 94 acres near Holland Landing just four months after the highway was announced.
The Ford government also sought to shield both projects from federal environmental oversight. After Canada's Impact Assessment Agency initially designated Highway 413 for review, the federal and provincial governments struck a deal in March 2024 to drop the federal assessment. In December 2024, the Impact Assessment Agency formally rejected requests from environmental groups and First Nations for a renewed review. For the Bradford Bypass, a federal court judge ruled in April 2023 that the federal government had acted "unreasonably" in denying an environmental assessment — but ultimately no meaningful review has been conducted.
Legal actions
In April 2023, Federal Court Justice Angela Furlanetto ruled that Environment Minister Steven Guilbeault had acted "unreasonably" under the Impact Assessment Act when he declined to designate the Bradford Bypass for a federal environmental review. The court found the decision failed to properly account for the project's potential impacts on federal jurisdiction areas including fisheries and migratory birds. Despite the ruling, the project has continued to advance without a comprehensive updated environmental assessment — the existing EA dates to 1997.
In December 2024, Canada's Impact Assessment Agency formally rejected calls from environmental groups, First Nations communities, and hundreds of scientists for a federal environmental review of Highway 413. This came after the federal government struck a deal with Ontario in March 2024 to drop an earlier designation, agreeing instead to a weaker "collaboration" framework. Critics argued the federal government effectively abdicated its environmental oversight responsibilities under political pressure from the Ford government.
Ford's government passed Bill 5 in 2025, which critics described as designed to fast-track Highway 413 construction while further limiting environmental oversight and public challenge mechanisms. The legislation stripped away additional procedural protections and shortened timelines for reviews, enabling construction to commence before environmental and Indigenous consultation processes were fully resolved. Environmental groups challenged the law's compatibility with federal environmental obligations.
Government activity on this file
via PoliMon · updated hourly- Newsroom · Highway 413changedOntario Begins Construction on New Bridges to Support Future Highway 413 CorridorNov 13, 2026What changed
-“Gridlock is costing our economy billions of dollars every year, and keeping drivers from spending precious time with family and friends” said Prabmeet Sarkaria, Minister of Transportation. “With construction now underway on two new bridges, we're making real progress to build Highway 413 and get people and goods moving faster across the GTA . We're building the infrastructure our growing communities need to support a stronger, more competitive and self-reliant economy.” The new bridges at Highway 10 and Bovaird Drive will prepare the corridor for construction of Highway 413. At Highway 10, crews will build a new bridge over the future highway, while work at Bovaird Drive will include a new bridge over the highway, in addition to widening Bovaird Drive and creating a grade separation from Heritage Road to Mississauga Road to prepare for a future interchange at Highway 413. Ontario is also advancing construction on the broader Highway 413 corridor. The province recently issued a Request for Proposals ( RFP ) to design and build the eastern section of Highway 413 from Highway 400 to west of The Gord Road. The RFP also includes the extension of Highway 427 from Major Mackenzie Drive north to Highway 413. Once complete, the new highway will extend from Highway 400 in the east to the Highway 401/407 ETR interchange in the west, with 11 interchanges at municipal roads and connections to Highways 410 and 427.+“Gridlock is costing our economy billions of dollars every year, and keeping drivers from spending precious time with family and friends” said Prabmeet Sarkaria, Minister of Transportation. “With construction now underway on two new bridges, we're making real progress to build Highway 413 and get people and goods moving faster across the GTA . We're building the infrastructure our growing communities need to support a stronger, more competitive and self-reliant economy.” The new bridges at Highway 10 and Bovaird Drive will prepare the corridor for construction of Highway 413. At Highway 10, crews will build a new bridge over the future highway, while work at Bovaird Drive will include a new bridge over the highway, in addition to widening Bovaird Drive and creating a grade separation from Heritage Road to Mississauga Road to prepare for a future interchange at Highway 413. Ontario is also advancing construction on the broader Highway 413 corridor. The province recently issued a Request for Proposals ( RFP ) to design and build the eastern section of Highway 413 from Highway 400 to west of The Gore Road. The RFP also includes the extension of Highway 427 from Major Mackenzie Drive north to Highway 413. Once complete, the new highway will extend from Highway 400 in the east to the Highway 401/407 ETR interchange in the west, with 11 interchanges at municipal roads and connections to Highways 410 and 427.
- Newsroom · Highway 413newOntario Begins Construction on New Bridges to Support Future Highway 413 CorridorNov 13, 2026
…nstruction now underway on two new bridges, we're making real progress to build Highway 413 and get people and goods moving faster across the GTA . We're building the infr…
Rippling effects
In August 2025, Ford awarded the first construction contracts for Highway 413 — an embankment at the Highway 401/407 interchange and road resurfacing on Highway 10 in Caledon — formally beginning construction despite no completed independent cost-benefit analysis and unresolved concerns from environmental groups, First Nations, and scientists. A January 2026 internal government report obtained by journalists admitted the highway would have devastating environmental impacts, contradicting the government's own public messaging.
Transportation experts consistently warn that building new highways to relieve congestion triggers "induced demand" — the well-documented phenomenon in which new road capacity generates new car trips, filling the new lanes within five to ten years and returning congestion to pre-highway levels. The government's own internal traffic forecasts project "crushing gridlock" ahead even with Highway 413 built.
Both highways serve a secondary function beyond moving cars: they enable and accelerate low-density sprawl development on the urban fringe. The corridors open up Greenbelt-adjacent land for subdivision development, converting farmland and wetlands into subdivisions, and generating enormous profits for the developers who own land along the routes — many of whom, as documented, are major PC donors. This connects Highway 413 and the Bradford Bypass directly to the broader Greenbelt scandal as instruments of the same developer-first land-use agenda.
The combined cost of both projects — potentially $10–16 billion of public funds — crowds out spending on transit, healthcare, and education at a time of severe provincial fiscal pressure. Ontario's Auditor General and independent analysts have called both projects a misuse of public funds, noting the money could fund transformative transit expansions that would benefit far more commuters across a far greater area. Ford has committed tens of billions to roads, while repeatedly delaying, cancelling, or downloading costs for transit expansion across the region.
Linked bills
Sources
- National Observer — Developers with ties to Ford government stand to cash in on Hwy. 413
- National Observer — Feds drop Greenbelt impact assessment for Ford's Highway 413
- National Observer — Feds rule out environmental assessment on Ford's Highway 413 — for good
- National Observer — How Bradford Bypass became a pork barrel for Ford's rich developer donors
- The Narwhal — Highway 413 and Bradford Bypass: a guide to Ford's controversial plans
- The Narwhal — Construction starting on Highway 413: what you need to know
- The Narwhal — Bradford Bypass federal review rejected
- The Trillium — Internal Ontario government traffic forecast shows crushing gridlock ahead — even with the 413
- The Pointer — Highway 413 & Doug Ford's developer-driven transportation planning
- The Pointer — Bradford Bypass will devastate the Holland Marsh and do nothing to fix congestion
- Ontario NDP — Ford's PCs took $753,000 in donations from developers for the 413
- CBC News — Construction starts on Highway 413
- Environmental Defence — Highway 413 Environmental Impacts
- National Observer — New traffic study shows Ontario's Highway 413 not needed
- Ontario Taking Next Steps to Build Highway 413 — Ontario Newsroom
- Ontario Auditor General Tables 2025 Annual Report — Office of the Auditor General of Ontario (CNW release)
- AECOM-led joint venture appointed as program management consultant for Ontario's Highway 413 — AECOM
- Ontario Newsroom: Ontario Begins Construction on New Bridges to Support Future Highway 413 Corridor
- CBC News video (via Yahoo News): Ontario says 2 Highway 413 bridges now being built



