Ontario Science Centre — Manufactured Closure & Ontario Place Relocation
$500M+Cost to Ontario
19 sources ↓TL;DR
Ford abruptly closed the Ontario Science Centre on June 21, 2024, citing a dangerous roof — but the engineers' own report did not recommend closure. The same roofing material exists in 400+ other Ontario buildings that remain open. The roof survived a major snowstorm intact. Ford refused to reopen it anyway. The Science Centre is now temporarily housed in a mall and at Harbourfront while a replacement is built at Ontario Place — a project whose cost has ballooned from $322 million to over $1 billion, with the new building 45% the size of the original.
What was promised
Surma promised an interim Science Centre facility after closing the Don Mills site
“In the meantime, we are making every effort to avoid disruption to the public and help the Ontario Science Centre continue delivering on its mandate through an interim facility, as well as alternative programming options.”
Kinga Surma, · Ministry of Infrastructure news release
What happened · Jun 29, 2026
An interim Science Centre opened at Harbourfront Centre on June 29, 2026, about two years after the Don Mills closure.
The Science Centre's KidSpark space opened at Harbourfront Centre in December 2024, and a pop-up ran at CF Sherway Gardens until January 4, 2026. On December 10, 2025, Tourism Minister Stan Cho announced that an interim location would open at Harbourfront Centre 'by summer 2026'. On June 29, 2026 the province opened the first phase of the interim site. It said the site would cover about 86,000 square feet once fully running (the Don Mills building was about 568,000 square feet) and would operate until 2029.
Promise: Ontario Newsroom
Outcome: Ontario Newsroom, Ontario Newsroom, Global News
Ford government said the new Ontario Place Science Centre could open as early as 2028
“Infrastructure Ontario will be releasing a Request for Proposals to help identify a temporary location for the Ontario Science Centre, while work continues to build a new permanent home for the Science Centre at Ontario Place with an opening slated for as early as 2028.”
Ministry of Infrastructure news release, · Ministry of Infrastructure news release
What happened · May 25, 2026
2028 hasn't arrived, but the government's own releases now say the new centre is on track to open in 2029.
In its December 3, 2024 Ontario Place audit, the Auditor General wrote that 'The new building is expected to open in 2029', using a date supplied by Infrastructure Ontario. On February 26, 2026 the province awarded the $1.04 billion construction contract and said the building would be finished 'as early as 2029'. On May 25, 2026 the province broke ground and said the facility 'is on track to open in 2029'. The province also says the interim Harbourfront Centre site will run until 2029.
Surma said moving the Science Centre would save taxpayers $257 million
“The business case confirms that the relocation will save Ontario taxpayers $257 million over a 50-year period when compared to the cost of remaining at the current site and will also provide a greater share of space for programming than is the case at the current site.”
Kinga Surma, · Ministerial statement, Ontario Newsroom
What happened · Dec 3, 2024
The Auditor General found the relocation's estimated cost had risen $397 million (47%) to $1.444 billion by November 2023, but said the cost of staying would also have risen, without giving a figure.
The March 2023 business case put the cost of staying at Don Mills at $1.304 billion and the cost of moving to Ontario Place at $1.047 billion (both 50-year net present value), a gap of $257 million. On December 3, 2024 the Auditor General reported that 'As of November 2023, based on the latest available cost information, the total cost estimate for building and maintaining the new OSC at Ontario Place increased by $397 million (or 47%)... If these costs are added to the $1.047 billion above, the total is now $1.444 billion.' The Auditor added that 'costs of rehabilitating and remediating the existing OSC site would also have increased', without giving a figure. In February 2026 the province signed a fixed-price $1.04 billion contract to design, build, finance and maintain the new building, which is a different basis from the 50-year estimate.
Promise: Ontario Newsroom
Outcome: Office of the Auditor General of Ontario, Global News
Ford said he wanted to make sure all 400 Science Centre workers stayed employed
“I want to make sure all 400 people there are going to be employed.”
Doug Ford, · Press conference, Scarborough
What happened · Sep 10, 2026
On September 10, 2026 the Ontario Science Centre laid off about 30 workers, including its entire science department.
After the Don Mills site closed in June 2024, contractor food-service and cleaning staff were laid off. On September 12, 2024 Ford said of the cleaners, 'We'll find jobs for those people within the system'; in November 2024 the head of OPSEU Local 549 said that never happened. On September 10, 2026 the Science Centre laid off 30 workers, including the entire science department (OPSEU later put the number at 31: 27 permanent and four contract roles). The Tourism minister's office said 'New roles will be available for some of the impacted individuals' at the interim and permanent sites. OPSEU said only one of the 30 had been offered another permanent public-service job, and that the cuts took the unionized workforce from 166 to 136.
Ford government said the Science Centre would stay open until its replacement opened
ParaphraseConstruction on the new facility is slated to begin in 2025, with its opening expected in 2028. The existing Science Centre will remain open to the public until then, the province says, and then it will be demolished.
the province, as reported by CBC News, · Ontario Place news conference
What happened · Jun 21, 2024
The province had the Science Centre closed with less than two hours' notice on June 21, 2024, years before any replacement was built, after an engineering report that did not itself recommend full closure.
On June 21, 2024 the province announced the Ontario Science Centre would close immediately, citing an engineering report on its RAAC roof panels; the Ministry of Infrastructure urged the centre's board to shut it, and the board did. The report rated 2-6% of roof panels high-risk and safe only until Oct. 31, 2024, and did not specifically recommend closing the building; the province put roof repairs at $22-40 million. In December 2024 the Auditor General reported the new Ontario Place building is expected to open in 2029, and that building and maintaining it would cost about $1.4 billion, more than the $1.3 billion estimate for keeping the old site. Ground was broken at Ontario Place on May 25, 2026.
Who benefited
- Ontario Science Partners · $1.04B
Awarded a fixed-price $1.04B design-build-finance-maintain contract (Feb 26, 2026) for the new Ontario Science Centre at Ontario Place, the relocation that followed the Don Mills closure. Procurement was described as competitive.
Source: New Ontario Science Centre Contract Awarded - Infrastructure Ontario (2026-02-26), New science centre will be built as early as 2029 with construction beginning in spring - CBC (2026-02-26)
Who was hurt
- Ontario Science Centre
Provincial agency closed from its Don Mills building with only a few hours' warning in June 2024 and, in Sept 2026, laid off 30 workers including its entire science department (CP).
Source: Ontario Science Centre laying off entire science department - CP/CP24 (2026-09-10), Ontario to open temporary science centre at Harbourfront Centre next summer - CBC (2025-12-10)
Key: People Related scandals
The web
2 peopleWhy it matters
The closure did not happen in isolation. It was announced in the context of the Ford government's plan to relocate the Science Centre to Ontario Place — the same waterfront site at the centre of the Therme spa deal — and to demolish the original Don Mills building. The closure and relocation were announced together, suggesting the safety rationale was constructed to justify a decision that had already been made for other reasons: the Science Centre's Don Mills location needed to be vacated to facilitate the broader Ontario Place redevelopment.
The financial case for relocation collapsed on examination. The Ford government had argued that repairing and renewing the existing Science Centre would cost $478 million — more than building new. The Auditor General's December 2024 report found that this framing was misleading: the government's own business plan had projected $257 million in savings over 50 years from relocation. By the time the AG reported, relocation costs had already exceeded $400 million — more than the cost of simply repairing the roof. The numbers had inverted: the move was more expensive than the repairs it replaced.
Then came the contract. In late 2025, Ford's government awarded a $1.04 billion contract to build the new Ontario Place-based Science Centre — more than three times the original $322 million projection, and double the "over $500 million" figure cited in the Auditor General's own December 2024 report. The new building will be 45% the size of the original. Ontarians are paying three times as much for less than half the institution. The Auditor General had already found the decision-making process "not fair, transparent or accountable" — the same language used to describe the Therme lease that surrounds the new site.
The original building — designed by Raymond Moriyama and recognized as an architectural landmark — now sits empty and deteriorating at Don Mills, with demolition planned. Community groups, architects, heritage advocates, and former Science Centre staff have organized against the demolition. A year after the closure, staff described the closure as "the biggest betrayal" — abrupt, unexplained, and irreversible by the time anyone could mount a challenge.
Legal actions
In the Auditor General's December 2024 report on Ontario Place, she found the Science Centre relocation had already cost more than the government's projected savings from the move — $400M+ spent versus $257M in anticipated 50-year savings. The report found the decision-making process was "not fair, transparent or accountable." Shortly after the AG report, the government awarded a $1.04 billion construction contract for the new Ontario Place-based Science Centre — more than three times the original $322M projection, and double the "over $500M" figure the AG herself had cited just weeks earlier. The new building will be 45% the size of the original.
Engineering Reports Show Closure Was Not Recommended — FOI Documents Reveal (opens in a new tab)
CompletedDocuments obtained through Freedom of Information requests and published by Canadian Architect revealed that draft engineering reports from Rimkus Consulting — the firm hired to assess the Science Centre roof — did not recommend closure. The "high-risk" RAAC panels covered less than 2.5% of the roof, concentrated in non-exhibition areas, and early draft reports recommended routine targeted repairs over the summer. The final report, released only after the closure announcement, was more alarming in tone. Texts between Infrastructure Ontario's CEO and communications staff indicated the Ministry's communications team was involved in how the engineers' findings were framed for public release — raising questions about whether political staff shaped the public safety rationale for a decision made for other reasons.
In early 2025, the Ontario Science Centre's roof — the stated reason for its permanent closure — withstood record snow loads from a major snowstorm without structural incident. Infrastructure Ontario confirmed it could not say whether the roof had been damaged. Liberal MPPs called on the government to reopen the building given the roof's demonstrated performance. Ford refused, stating the closure decision stood regardless of the roof's actual behaviour under stress. Critics noted that the government's refusal to revisit the decision, even after the stated safety risk failed to materialize, was evidence that the closure had never truly been about the roof.
Government activity on this file
via PoliMon · updated hourly- committees · Ontario Place, Ontario Science Centre, Ring of Fire, Ontario Line, Metrolinx, development charges, Auditor General, affordable housing, First NationnewStanding Committee on Heritage, Infrastructure and Cultural Policy 2026-10-28Nov 3, 2026
…in Toronto; —contract execution for the new Ontario Science Centre facility at Ontario Place; —contract execution for the Stevenson Memorial Hospital redevelopment project…
Rippling effects
While the new Science Centre is under construction — with a target opening date of 2028–2029 — Ontario's public science institution now operates as a pop-up in a former Nordstrom store at Sherway Gardens mall and a temporary display at Harbourfront Centre. This is the province's interim provision for what was one of Canada's premier science education institutions. Schools that previously relied on the Science Centre for curriculum programming have lost access to the permanent facility indefinitely.
The broader context is the Ontario Place redevelopment: the new Science Centre will occupy a fraction of the Ontario Place site, while the majority of the publicly owned waterfront is leased to Therme for a private spa — on a 95-year lease, for $1 per year, with $2.24 billion in taxpayer-funded infrastructure. The Science Centre was used to provide public-interest cover for the Ontario Place deal: a public institution embedded in a private redevelopment project, allowing the government to claim the waterfront remains publicly accessible while the dominant land use is a private luxury facility.
The demolition of the Moriyama-designed original building, if it proceeds, will be permanent. The architectural and cultural loss cannot be recovered. Heritage Ontario and architectural organizations have documented the building's significance; Moriyama himself designed it as a building that was meant to feel like science itself — layered, surprising, and organic. The replacement, by contrast, will be a fraction of the size, embedded in a commercial development, and built at a cost that has already exceeded any plausible economic justification.
Sources
- Ontario Science Centre laying off entire science department — The Canadian Press (via CP24)
- Wikipedia — Ontario Science Centre
- Canadian Architect — Ontario Science Centre doesn't require full closure: engineers' report
- Canadian Architect — Draft engineering reports didn't suggest closure, new documents reveal
- Canadian Architect — Cost of temporary location exceeds cost of roof repairs
- Canadian Architect — $1.04B contract awarded for new Ontario Science Centre
- CBC — Hundreds of buildings use Science Centre roofing panels; none have been closed
- CBC — Science Centre roof passes snowstorm test; Ford still refuses to reopen
- CBC — Ontario Science Centre to close immediately as province cites roof concerns
- CBC — How much of the Ontario Science Centre roof is actually at risk?
- CBC — New Science Centre will be built at Ontario Place as early as 2029
- CBC — Ontario to open temporary science centre at Harbourfront Centre
- Global News — Ford government awards $1B contract for new Ontario Science Centre
- Global News — Infrastructure Ontario can't say if Science Centre roof was damaged in snowstorm
- Global News — Schools with same roof panels have no budget to replace them
- Link2Build — A year on, staff grieve Ontario Science Centre's snap closure
- The Architect's Newspaper — Public outrage continues over Ontario Science Centre demolition plans
- Infrastructure Ontario — RAAC Roof Panel Assessment Final Report (June 2024)
- CTV News: Cost to rename Science Centre Station adds up to more than $600K: documents

