Eglinton Crosstown: Six Years Late, $1 Billion Over Budget, and Ford Refuses an Inquiry

TL;DR

Toronto's Eglinton Crosstown LRT opened on February 8, 2026, six years behind schedule and, according to a Metrolinx report cited by The Canadian Press, at a cost of over $13 billion, a billion more than its revised budget. Two days earlier Premier Doug Ford rejected calls for a public inquiry, saying he would not "waste time on inquiry and all the nonsense."

Connections graph

Key: People Related scandals

Why it matters

The Eglinton Crosstown is one of the most troubled transit builds in Ontario's history. The Canadian Press reported that a Metrolinx report last fall put its cost at over $13 billion, a billion more than the revised budget set out in a 2018 Auditor General's report. CBC News noted the line was initially pegged at $4.6 billion and was expected to be finished by 2020. It opened in February 2026, six years late.

When asked whether he would call a public inquiry, Premier Doug Ford said no. "I'm the first to come out and acknowledge the mistakes, but I'm not going to waste time on inquiry and all the nonsense, tie all these people up," he told reporters on February 6, according to CBC News. "No, we aren't going to do that, we're going to move on and continue building the subways," he said, as reported by Global News. When reporters pressed him, he said: "Guys, you're beating a dead horse here."

Ford's answer was that the lessons are already known. "We all know the mistakes and we've acknowledged them, and we've learned," he said, according to CTV News, and Metrolinx CEO Michael Lindsay echoed his message about moving forward instead of reviewing the mistakes. But those lessons have not been set out in public. CityNews reported that information on the exact nature of the line's problems "hasn't been routinely disclosed," and that the government backed away from providing projected and revised opening dates as issues arose. NDP Leader Marit Stiles partly blamed the public-private partnership model, saying "nobody can ever give you any answers" and "There is zero accountability."

The line was delivered as a public-private partnership. CTV News reported that Metrolinx contracted Crosslinx Transit Solutions in July 2015 to design, build and finance the line under a fixed-price agreement, and that the project was delayed by more than 260 construction deficiencies, legal disputes between Metrolinx and the consortium, COVID-19 disruptions, and software and signalling problems. Ford said the Crosstown's mistakes will be avoided on the projects now underway, such as the Scarborough subway extension and the Ontario Line, according to CTV News. See the Ontario Line cost overrun and the Metrolinx GO expansion write-off.

Rippling effects

The calls for an inquiry came from the NDP, the Liberals, a city councillor and transit riders' advocates. On January 22, 2026, Liberal MPPs Adil Shamji and Andrea Hazell demanded a public inquiry, compensation for businesses hurt by construction, and a rapid-response task force for the line's launch, as reported by CBC News and CityNews. Shamji called Ford's oversight of the project "a case study in mismanagement." A provincial spokesperson answered that the Ford government had brought the line to "substantial completion after years of neglect and delays by the previous Liberal government."

Toronto councillor Josh Matlow launched a petition calling for an inquiry in October 2025, according to CBC News. On opening day he told The Canadian Press: "Public agencies and governments need to answer when things go wrong. Why did the cost go up over a billion dollars? What were the actual reasons for the delays?" TTCriders executive director Andrew Pulsifer told Global News an inquiry into Lines 5 and 6 was needed so that future projects "are not saddled with the same mistakes."

The cost was also borne along the corridor. Stiles told CP24 that about 300 businesses in the Little Jamaica area around Eglinton went under during construction, according to the Toronto Sun, which also reported that Hazell vowed to keep pushing for a public inquiry. University of Toronto infrastructure expert Matti Siemiatycki told CTV News there was "overconfidence in the public-private partnership model" and called the opening "a look-in-the-mirror moment."

Sources

  1. The Eglinton Crosstown LRT is more than $1B over budget. Ford says he won't waste time on an inquiry — CBC News
  2. Ontario won't order inquiry into Eglinton Crosstown LRT — Global News
  3. Ford rules out public inquiry as officials laud completion of Eglinton Crosstown — CTV News
  4. Eglinton Crosstown LRT riders cheer as long-delayed transit line finally starts service — CTV News / The Canadian Press
  5. A look in the mirror: the lessons buried beneath the Eglinton Crosstown LRT — CTV News
  6. Eglinton LRT finally opens with many lining up to ride first train — Toronto Sun
  7. Ontario Liberals demand public inquiry into Eglinton Crosstown LRT construction delays — CBC News
  8. Ontario Liberals reiterate Eglinton Crosstown LRT public inquiry push, call for 'rapid response' team after launch — CityNews Toronto
↑↓ move↵ focus⌘↵ open page→ start a path from here